Dismantling of Kalibata Bridge Stagnated
access_time March 10 2016 10:13 AM remove_red_eye 1569
Reported by Aldi Geri Lumban Tobing | Translated by Nugroho Adibrata
Reported by Aldi Geri Lumban Tobing | Translated by Nugroho Adibrata
Dismantling process of Kalibata Bridge, Rawajatim, Pancoran, South Jakarta had to be postponed and wait for garbage transportation under bridge is completed.
The problem is floodwater and garbage from Bogor, thus we have to do dredging first and continued with dismantling," he told, Wednesday (3/9).
Implementer of Dismantling in Kalibata Bridge, Iksan Masduki said one unit of breaker should work interchangeably with one unit of backhoe to pick up garbage from Ciliwung River.
Kalibata Bridge Demolished"The problem is floodwater and garbage from Bogor, thus we have to do dredging first and continued with dismantling," he told, Wednesday (3/9).
He expressed, such dismantling is predicted to be complete within 15 days ahead.